Saturday 18 July 2009

16th July 2009



There is plenty of flow (kWs!) over the weir following the recent heavy rain


Ann & Helen discuss progress with Richard of LMV (Lakeland Marine Construction)
On the left of the picture you can see the reinforcement being laid prior to pouring the next part of the inflow slab.
The large plastic pipes will allow water to be diverted along the old millrace





Saturday 4 July 2009

2nd July 2009





Plastic piles and a concrete wall are being installed to stop water percolating through the soil of the island between the river and the channel that will feed the hydro.
Bottom picture features Settle Hydro Director, Ann Harding, surveying the work.