Friday, 28 August 2009

20th August 2009

The concrete slab on which the Power House will be built will span the walls that can be seen in this picture.


The Screw trench has been extended to the edge of the river. Bed rock has been reached and so further excavation is going to be a noisy process!




On target for delivery of screw by mid September and commencement of electricity generation by end October.


The team have been giving some time to think about how we can maximise the educational and visitor attraction value of the scheme once we are operational. A number of initiatives are being investigated and costed and a funding application being prepared

We hope to install a number of webcams that will enable us to show the operation of the screw on our website. The webcams will also provide us with a remote monitoring facility that will enable us to readily check that every thing is operating as it should.

We are planning to install equipment that will enable us to display the amount of electricity being generated at that point in time and the total number of kWh generated to date.

An Information Board and leaflets will be designed and produced to explain how the scheme works and to highlight other aspects of the site such as the old mill and waterwheel and the fish pass.


8th August 2009

The reinforced concrete walls of the inflow channel have now been completed and excavation of the trench that will house the Screw has started.


This reinforcing mesh laid on the ground indicates where the trench for the screw will be excavated.


Helen & Richard (from LMC) survey the work




The trench will enter the river just to the left of where Helen and Richard are standing














Saturday, 18 July 2009

16th July 2009



There is plenty of flow (kWs!) over the weir following the recent heavy rain


Ann & Helen discuss progress with Richard of LMV (Lakeland Marine Construction)
On the left of the picture you can see the reinforcement being laid prior to pouring the next part of the inflow slab.
The large plastic pipes will allow water to be diverted along the old millrace





Saturday, 4 July 2009

2nd July 2009





Plastic piles and a concrete wall are being installed to stop water percolating through the soil of the island between the river and the channel that will feed the hydro.
Bottom picture features Settle Hydro Director, Ann Harding, surveying the work.

Thursday, 25 June 2009

25th June 2009





Hi, Steve here - that's me in the top picture!. Have just returned from a visit to the site. Work to date has concentrated on excavating the millrace immediately after the incoming sluice gate - see 2nd picture. It's wet work!

Thursday, 18 June 2009

18th June 2009

Settle Hydro is GO!

Work started today on-site at Settle Weir.